Short answer: measure each run structure to structure by size and material, get depth from the profile, count every structure from both the plan and the structure table, convert to trench and bedding quantities, then add connections, dewatering, outlet protection, restoration and testing.

1. Find the storm sheets and the drainage notes

Storm drain usually lives on the grading and drainage plan, storm plan and profile sheets and the detail sheets, with requirements in spec section 33 41 00. Note the allowed pipe materials (RCP class, HDPE, PVC), joint type, bedding class and whether video inspection is required.

2. Measure runs structure to structure

Measure each run from center of structure to center of structure, unless the spec pays to inside face. Record size, material and class for each run. Larger RCP is heavy, so production drops and equipment size goes up as diameter increases.

3. Get depth from the profile, not the plan

Use rim and invert elevations to find the cut at each end, average them, and group the footage by depth band. Storm lines are often shallow at the inlet and deep at the outfall, so one run can cross two bands.

4. Count every structure by type

Curb inlets, drop inlets, junction boxes, manholes, headwalls, flared end sections, outlet protection (riprap), and trash racks. Check the structure table against the plan; tables and plan callouts don't always agree, and that's a question for the engineer before bid.

5. Trench, bedding and backfill

Large-diameter pipe needs a wider trench. A common rule is outside diameter plus 1 to 2 feet on each side, but follow the detail. Bedding and pipe-zone stone add up fast on 36-inch and larger pipe. Check one run in the trench calculator.

6. Don't forget the edges

Connections to existing structures, temporary drainage during construction, dewatering, outlet erosion protection, pavement patch over the trench, and CCTV or mandrel testing at the end. These are the items that turn a winning storm number into a losing job.

Worked example (demonstration)

Demonstration numbers, not a customer project: a 24-inch RCP line runs 280 ft between two curb inlets and a junction box, then 60 ft to a headwall. Cut ranges from 5 ft to 9 ft, so 180 ft falls in the 0–6 ft band and 160 ft in the 6–10 ft band. The structure table lists 2 inlets, but the plan shows 3. That gets an RFI before the bid, not a surprise in the field.

Trench calculator

Check a run's quantities.

Scope checklist

38 items to check before bid day.

Utility estimating guide

Sewer, water and storm, step by step.

Let AI trace the storm runs

Precision Bid Win measures RCP and HDPE runs, counts inlets and headwalls and links each quantity to its sheet for checking.