Free estimator tool

Trench excavation calculator

OSHA soil slopes, real pipe outside diameters, bedding, backfill, haul-off trucks and cost per foot — with every step of the math shown so you can check it.

Load a typical job

5 ft or deeper: OSHA 1926.652 requires sloping, benching, shoring or a trench shield unless in stable rock.

Results

Excavation
692.6 BCY
Bedding & pipe zone (net)
168.8 CY · 236.4 tons
Backfill above pipe zone
517.1 CY
Spoil haul-off
219.3 LCY
Truck loads
19
top 14.0 ftbottom 3.0 ft
Blue = bedding & pipe zone. Grey = backfill.

Show my math

  1. 1. Top width = 3.0 + 2 × 1 × 5.5 = 14.00 ft
  2. 2. Excavation = 400 × 5.5 × (3.0 + 14.00) ÷ 2 ÷ 27 = 692.6 BCY
  3. 3. Pipe OD = 9.05 in · pipe-zone height = (6 + 12) ÷ 12 + 0.754 = 2.25 ft
  4. 4. Pipe zone = 400 × 2.25 × (3.0 + 1 × 2.25) ÷ 27 = 175.5 CY
  5. 5. Pipe volume = 400 × π × (0.377)² ÷ 27 = 6.6 CY → net bedding 168.8 CY (× 1.4 t/CY = 236.4 t)
  6. 6. Backfill = 692.6 − 175.5 = 517.1 CY
  7. 7. Haul-off = 175.5 BCY displaced × (1 + 25%) = 219.3 LCY ÷ 12 CY = 19 loads

Assumes native backfill is reused above the pipe zone and all pipe-zone material is imported. Bedding density 1.4 tons/CY is a typical crushed-stone value — check your supplier. RCP OD uses ASTM C76 Wall B. This is a planning tool; it is not an OSHA competent-person determination.

Skip the hand math on the whole plan set

Precision Bid Win measures every run from your PDF plans and feeds trench quantities straight into the estimate, crews and schedule.